The Hermantown City Council has two data center items on its agenda for Monday, Oct. 5, at 6:30 p.m. Neither one approves Google's data center. Resolution 2026-124 would adopt the final environmental review for the site in the southwest corner of the city. Resolution 2026-125 would approve the route for the Minnesota Power transmission lines that would serve it. The city has said it won't act on the project itself until environmental review is complete. That makes these two votes the step the rest of the process has been waiting for.
That includes the courtroom. One of the two lawsuits over the project was paused in May until the city finished this exact review. So the most important thing to know about Monday is what it would finish, more than what it would approve.
What's on the agenda, and what isn't
The agenda went up on the city's CivicClerk portal Oct. 1. It also includes a Google project update from company representatives. Here is how the pieces of the project line up right now.
| Decision | Status as of Oct. 4, 2026 |
|---|---|
| Final AUAR and mitigation plan, Resolution 2026-124 | On the Oct. 5 agenda |
| Minnesota Power 230-kV line route, Resolution 2026-125 | On the Oct. 5 agenda |
| Special use permit for the data center | Not scheduled |
| Development agreement and tax abatement agreement | Tabled after the May 4, 2026 public hearing, not scheduled |
The two agreements are where the money questions sit. In earlier versions reported by the Duluth News Tribune, they included $4.5 million in payments to the city over 20 years and $42 million for the Hermantown school district over 28 years. KAXE reported the school figure as $40 million in May. Neither agreement is up for a vote Monday.
What the review studied, and why it's the second one
AUAR stands for Alternative Urban Areawide Review, a Minnesota environmental study that looks at a whole area at once. Hermantown already adopted one for this site in October 2025. The city then restarted the process with Google. Mayor Wayne Boucher announced the restart at the State of the Cities address on March 12, 2026, and four days later the council hired Braun Intertec Corporation to do an independent technical review. The new study covers 26 parcels totaling 278 acres, a smaller area than the 2025 version. If the council adopts it Monday, the 2026 AUAR replaces the 2025 one entirely.
The comment record shows how much public input went into it. The draft drew comments from 5 government agencies, along with 235 public comments. Consultant Kimley-Horn sorted them into themes ranging from groundwater and wetlands to transparency and requests for a full Environmental Impact Statement.
The Minnesota Department of Natural Resources was the main hurdle. No state agency filed a formal objection by the Aug. 25 deadline. That same day, though, the DNR sent a letter raising concerns about wetlands and cold-water trout streams. City staff, Google's representatives, and Braun Intertec met with DNR staff on Sept. 2. The city replied in writing on Sept. 4, and on Sept. 10 the DNR wrote back that the city's letter "directly responded" to its concerns. That exchange explains why the vote is landing now and not in August.
The project under review has gotten smaller
The design the AUAR measures against has shrunk since the study began. The August 2026 application shows three data center buildings totaling 1.66 million square feet. The AUAR studied a scenario of four buildings and 1.80 million square feet. Planned wetland impacts dropped from 32 acres in that scenario to 19.89 acres. The city's FAQ page still says "up to four data center buildings," which matches the study scenario and not the current application.
The site itself is 234 acres at the southwest corner of Midway and Morris Thomas roads. The application shows its main and emergency entrances on Morris Thomas Road. It includes a tree buffer of 20 to 50 feet along Midway Road, plus screening and noise walls along both Midway and Morris Thomas. The city says a traffic study is still checking whether that intersection needs a new signal. Locals call this corner the Adolph area. It sits next to Minnesota Power's Arrowhead Substation, which has been there since the 1970s, and that substation is the main reason the site is being considered.
The power line vote is a city decision for an unusual reason
The second resolution covers what would physically connect the data center to that substation: two parallel 230-kilovolt lines, about 1.6 miles of new high-voltage line inside city limits, plus new equipment at Arrowhead. A state law, Minn. Stat. § 216I.08, lets some transmission projects be reviewed and permitted locally. Hermantown agreed to take that role, so Minnesota Power doesn't need a separate route permit from the Minnesota Public Utilities Commission. That makes the city council the body deciding where these lines go.
The review behind that vote is a 429-page Environmental Assessment prepared with Kimley-Horn. It followed a public scoping meeting on Aug. 10 and was published in the state's EQB Monitor on Sept. 8. Its comment period has closed. The assessment calls most construction impacts short-term and minimal. It lists the lasting impacts as a change in the area's visual character, land permanently converted to a transmission corridor, and ongoing vegetation management. The resolution approves the assessment "subject to all future Project permits and approvals."
The Sept. 21 promises, and where they'll be tested
Google's most recent list of commitments came two weeks before this vote. At the Sept. 21 council meeting, Liz Schwab, who works in market development at Google, presented them in response to the DNR's concerns:
- A revised site plan with 37% less wetland impact than the original, plus new surface and groundwater data collection to help protect trout streams.
- Monitoring wells installed over the next several months, with data published every quarter once a baseline is set.
- An opt-in well program for neighbors within half a mile. If a well is affected, Google would pay for a replacement well, a connection to public water, or another agreed fix.
- An operating noise cap of 47 dBA, which Google compared to a refrigerator. The state standard cited in the presentation is 50 dBA.
- About $2.5 million in grants to local nonprofits for workforce, education, small business, and youth programs. Recipients will be named once the grants are final.
- Three options if the site ever closes: reuse by a new tenant, cleanup by the developer, or cleanup by the city, with that last option valued at about $210 million adjusted for inflation.
Schwab also announced a labor agreement between Mortenson, the project's builder, and the Duluth Building Trades Council. A final tree-planting plan was promised for October presentations. Schwab said she couldn't share the full agreement behind the decommissioning terms. The documents where commitments like these would normally be written down, the development agreement and the permit, are the items not yet scheduled.
Residents at the meeting were already asking about that gap. A Hermantown resident asked for a written guarantee that wells would be replaced if they went dry and wanted the state, not Google, to do the well testing. Another resident said they would not object if the data center were built along U.S. Highway 53 or in an industrial area, but considered this location the wrong spot. Brent Harju, a Hermantown resident speaking for Ironworkers Local 512, backed the project for its jobs and its effect on the tax base.
Why the lawsuits are tied to Monday, too
Two cases are pending. The first is MCEA and Stop the Hermantown Data Center v. City of Hermantown and Harmony Group LLC, case No. 69DU-CV-25-3448, filed in November 2025. MCEA is the Minnesota Center for Environmental Advocacy. In May, it said the two plaintiffs had agreed to pause the case while the city finished the updated AUAR. Under that arrangement, Harmony Group agreed not to start construction without giving MCEA time to seek an injunction. MCEA also said it could file a new challenge if the updated review fell short. Adopting the AUAR completes the document that case was paused to wait for.
The second suit, filed by Stop the Hermantown Data Center on April 29, 2026, raises separate claims of spot zoning, changes to the city's 2045 comprehensive plan, and open-meeting violations. The council met in closed session about pending litigation on Sept. 21, but the minutes don't say which case. The group describes itself as a nonpartisan residents' organization and is calling for a full Environmental Impact Statement.
The meetings after Monday
City calendars list these upcoming meetings:
- City Council: Oct. 19, Nov. 2, Nov. 16
- Planning and Zoning Commission: Oct. 20, Nov. 17
If the permit or the agreements come back, they would go through these bodies. Agendas and packets go up on Hermantown's CivicClerk portal, and the city keeps its timeline and documents on its project page.